2013 |
---|
CGS Representative appointed to SRG |
2014 |
---|
September |
Strategic Intent published on Web-Site |
June |
CGS meet with NKDC & LCC to explain vision |
November |
Governors agree to secure the land for CGS |
2015 |
---|
June |
Heads of Terms for Land Options drafted |
Solicitors & Land Agents appointed |
July |
CGS report to Governors on Sequential Test & Feasibility |
Wiverton appointed |
September |
Robert Carre Trust MAT formed with CGS & KSHS |
CGS commence bi-monthly meetings NKDC Planning |
October |
CGS meet with Stephen Phillips (MP) |
November |
Sequential Test & Feasibility completed by Wiverton |
Sport England contacted |
CGS visit to LCC to meet Katie Gosling |
2016 |
---|
July |
Submission to EFA for land acquisition |
Presentation to SRG on MAT / new site progress |
August |
NKDC & CGS produce design brief |
September |
Design Brief Consultation tendering commences |
CPMG & ARES appointed |
December |
Sketch proposals produced by CPMG |
Option to purchase land approved by EFA |
2017 |
---|
January |
GLLEP approached for funding (without success) |
Landowner appraised of current position |
EFA Grammar School Fund meeting (Kathryn Dixon) set up |
February |
CGS & CPMG presentation to NKDC Members |
Feedback expected late February |
March |
CGS & KSHS meeting with Justine Greening MP |
Visit to CGS by Caroline Johnson MP |
CGS & KSHS expected visit to DfE – awaiting date |